Holytown to Midcalder (H2M) Electrification 2015-2017


Involved in ECI Phase and Form 001 Design for 72 single track km (STK) route electrification project. Role included appraisal of ground conditions including mining and foundation design using PAN101 document.

During construction phase provided technical support to contractor.

Added value:

  • Initial MHB/ PBH involvement was driven by client request to augment the incumbent design team
  • Pragmatic approach to mining treatment
  • Technical support during construction stage such as retaining wall and slope stability

 

Client – PBH Rail